Starting at the base of the roofline, position the
trim against the battens and secure it using 40mm
galvanised nails. The trim can be butted together
or simply overlapped given the flexible properties
of the trims.
A section of the leg should be cut off to allow for
this overlap. The upper end of the trim is cut to
the required length and angle before nailing to
the battens.
A section of the leg should be removed to allow roof over-hang into the gutter.